Change orders

Draft, review and apply changes to a project contract, cost budget and completion date.

Use Project → Schedule → Change orders to record a scope, budget or schedule change. Drafting a change does not immediately update the project's totals.

Change order showing approved status, contract change and cost budget change
An applied change shows its commercial effect and status on the project.View full size (new tab)

Create a draft

  1. Choose New change order.
  2. Enter the Title, Description, Type and Reason.
  3. Enter the signed Contract change: positive for an increase, negative for a reduction.
  4. Enter the separate Cost budget change. An increase in the customer's price does not necessarily equal an increase in your cost.
  5. Add a New end date if the change moves completion.
  6. Choose Save change order.

Review the impact preview before submitting or approving. For example, a contract increase of 8,400 and a cost-budget increase of 6,000 affect different project totals.

Submit and review

Submit the draft when it is ready for an eligible reviewer. Submission notifies reviewers; rejection records a reason and notifies the requester. Actions shown depend on your permissions and the change's current status.

Approval asks you to confirm the resulting contract value, cost budget and end date. Once applied, the card shows Applied to project. A later Mark signed action records signature status; it is distinct from applying the financial change.

Keep the supporting scope

Use the drawing revision and measurement history to establish what changed, and a revised quote when the customer needs updated pricing. A change-order entry does not itself remeasure drawings or rewrite a customer quote.

Revised drawings and measurements · Quote revisions