Estimate costs and profit
Use Detailed estimating to compare estimated cost with the selling subtotal.
Open a quote and expand Detailed estimating → View costs and labor. This view explains the cost basis of the quote and its estimated profit before tax.
Read the estimate totals
| Total | What to check |
|---|---|
| Estimated cost | The material, other and labor costs included in the estimate. |
| Selling subtotal | The selling amount before the final quote-level adjustments. |
| Profit before tax | The estimate's selling return compared with the recorded costs. |
| Quote total | The customer-facing total after the applicable adjustments. |
Missing costs can overstate apparent profit. A fully priced selling quote is not necessarily a fully costed estimate.
Inspect a line
The breakdown shows base quantity and waste, final quantity, material or other cost, labor hours and rate, labor cost and total cost. Use Edit estimate for the row when available. A Source quantity fixed label means the quantity is tied to the takeoff source.
Read the pricing-mode explanation above the table. In one mode, selling amounts are derived from the cost estimate plus overhead. In another, costs and selling prices are separate, so editing cost preserves the selling price.
Markup and margin
Markup is profit divided by cost; margin is profit divided by selling price. For example, a cost of 100 and price of 125 gives 25% markup and 20% margin. Keep overhead, discounts and tax in view when comparing those numbers with a quote's final total.
Compare with delivery costs
This is estimated profit, not a record of actual job profit. After Start job, use Project costs to review purchase costs and allocations against the budget. Check unallocated and unreviewed costs before drawing conclusions about the job's actual performance.