Concrete Slab Calculator
Enter the slab size and thickness to get cubic yards, bag counts, ready-mix trucks and cost, plus the rebar grid or wire mesh and the gravel base under the slab.
Concrete Slab Calculator
Concrete, reinforcement and base for patios, driveways, garage floors and shop slabs
Slab Formula and Worked Examples
Thickness comes off the plans in inches, so divide by 12 before multiplying, then divide cubic feet by 27 for cubic yards. Add the waste allowance once, to the volume, before working out bags and trucks.
Example 1: 10 × 10 ft patio, 4 inches thick
1. Volume: 10 × 10 × 0.333 = 33.3 cu ft = 1.23 yd³
2. With 10% waste: 1.36 yd³ (36.7 cu ft)
3. Bags: 36.7 ÷ 0.60 = 62 bags of 80 lb mix, or 82 bags of 60 lb mix
4. Wire mesh: 100 sq ft ÷ 42.75 sq ft of new coverage per lapped 5 × 10 ft sheet = 3 sheets
5. Base at 4 inches: 100 × 0.333 ÷ 27 = 1.23 yd³ of stone before compaction
Example 2: 24 × 24 ft garage floor, 5 inches thick
1. Volume: 24 × 24 × 0.417 = 240 cu ft = 8.89 yd³
2. With 10% waste: 9.78 yd³, one 10-yard truck
3. #4 rebar at 12 in each way: 25 bars × 24 ft × 2 directions = 1,200 ft
4. Weight: 1,200 × 0.668 lb/ft = 802 lb, or 60 bars of 20 ft before laps
How Thick Should a Concrete Slab Be?
Choose thickness by what the slab carries. The International Residential Code sets 3.5 inches as the minimum for slab-on-ground floors (R506.1); the rows above that are common practice for residential flatwork, not code requirements. Structural slabs and anything carrying heavy equipment follow the drawings.
| Thickness | Typical use | Notes |
|---|---|---|
| 3.5 in | Code minimum for slab-on-ground floors | International Residential Code R506.1. Most residential flatwork is poured thicker than this. |
| 4 in | Patios, walks, shed pads, basement floors | The usual residential thickness. One cubic yard covers 81 sq ft. Wire mesh or fiber mix is common. |
| 5 in | Driveways and garage floors for cars | One cubic yard covers 64.8 sq ft. Rebar grids are common. |
| 6 in | Driveways for heavy pickups, RV and trailer pads | One cubic yard covers 54 sq ft. Often thickened at the edges. |
| 8 in and up | Equipment pads, loading areas, structural slabs | Design by the drawings or an engineer; thickness, mix and reinforcement come from the design. |
Rebar or Wire Mesh
Rebar grid
Bars both ways at a set spacing, commonly #3 or #4 at 12 to 18 inches on center. The calculator counts the span divided by the spacing, rounded up, plus one bar in each direction, then weighs it. Laps are not included; use the rebar calculator for laps and stock bars.
Welded wire mesh
Counted in 5 × 10 ft sheets. With a 6-inch lap on two edges, each sheet adds 4.5 × 9.5 = 42.75 sq ft of new coverage. Rolls and other sheet sizes change the count, so check what your supplier stocks.
| Bar size | Diameter | Weight per foot | 20 ft bar |
|---|---|---|---|
| #3 | 3/8 in | 0.376 lb | 7.5 lb |
| #4 | 1/2 in | 0.668 lb | 13.4 lb |
| #5 | 5/8 in | 1.043 lb | 20.9 lb |
Nominal weights from ASTM A615/A615M. Hold reinforcement up in the slab on chairs or bolsters; steel lying on the base does little.
The Gravel Base Under the Slab
Most exterior slabs sit on a compacted layer of crushed stone, and the calculator sizes it from the same footprint: length × width × base depth. A 4-inch base under a 20 × 20 ft slab is 4.94 cubic yards before compaction. Compacted stone takes more loose material than its finished volume, so add your supplier's compaction allowance, and use the gravel calculator to turn the volume into tons at the density your quarry quotes.
Interior slabs in conditioned space also need a vapor retarder: the International Residential Code (R506.2.3) calls for 6-mil polyethylene or an approved retarder with joints lapped at least 6 inches.
Common Slab Sizes
Concrete with a 10% waste allowance and bags at 0.60 cu ft per 80 lb bag, the yield in the Quikrete Concrete Mix data sheet. Rebar is a #4 grid at 12 inches each way, before laps.
| Slab | Thickness | Cubic yards | With 10% waste | 80 lb bags | Rebar (ft) |
|---|---|---|---|---|---|
| 10 × 10 ft | 4 in | 1.23 | 1.36 | 62 | 220 |
| 12 × 12 ft | 4 in | 1.78 | 1.96 | 88 | 312 |
| 12 × 20 ft | 4 in | 2.96 | 3.26 | 147 | 512 |
| 20 × 20 ft | 4 in | 4.94 | 5.43 | 245 | 840 |
| 24 × 24 ft | 5 in | 8.89 | 9.78 | 440 | 1,200 |
| 30 × 40 ft | 4 in | 14.81 | 16.30 | 734 | 2,470 |
Automate your slab takeoffs and quotes.
Spend less time measuring slab plans and rebuilding the same estimate. Get the next quote moving. BuildVision extracts slab areas and measurements from your plans and carries them through your rates and assemblies into a branded quote. Your team checks the quantities and pricing before sending. Try it free on your own plans.
How the Concrete Slab Calculator Works
A slab estimate is more than the concrete. The same length and width that set the yardage also set the rebar grid or mesh, the vapor barrier and the stone base underneath, so this calculator works them out in one pass. Enter the slab size, thickness, number of identical slabs and a waste allowance, then choose rebar, welded wire mesh or none.
Thickness drives the order more than anything else. Going from 4 to 6 inches is 50 percent more concrete, and a subgrade that runs half an inch low across a 30 × 40 ft shop floor adds almost two cubic yards. Settle the thickness for the use first (the guide on this page covers patios through equipment pads), then measure the real depth at the forms.
Rebar is laid out as a grid at the spacing you enter, with one more bar than spaces in each direction, and weighed at the ASTM A615 nominal weight for the bar size. Mesh is counted in 5 × 10 ft sheets with a 6-inch lap on two edges. The gravel base is the slab footprint times the base depth you enter, before any compaction allowance; size its tonnage with the gravel calculator.
Slab volume and material math
- Cubic yards = length (ft) × width (ft) × thickness (in) ÷ 12 ÷ 27
- Shortcut: cubic yards = square feet × thickness (in) ÷ 324
- Order volume = cubic yards × (1 + waste %)
- 80 lb bags = order ft³ ÷ 0.60; 60 lb bags = order ft³ ÷ 0.45
- Rebar bars each way = round up(span ÷ spacing) + 1; weight = length × lb/ft
- Gravel base (yd³) = length × width × base depth (in) ÷ 12 ÷ 27
Estimating Steps and Checks
Choose the thickness for the use
Patios, walks and shed pads are usually 4 inches; driveways and garage floors 5 to 6 inches; heavier loads follow the drawings. The International Residential Code sets 3.5 inches as the minimum for slab-on-ground floors.
Measure the slab at the forms
Measure length and width inside the set forms, then check the depth at the corners and middle. If the subgrade is low in places, use the average depth, not the plan depth.
Enter waste and the number of slabs
Add 5 to 10 percent for spillage and uneven subgrade, more for rough ground or thickened edges you have not measured separately. Enter how many slabs of the same size you are pouring.
Pick the reinforcement and base
Choose a rebar grid with bar size and spacing, welded wire mesh, or none for fiber mix. Enter the base depth to get the stone volume, or 0 to skip it.
Check the order against the supplier
Round the concrete to the increment your plant batches, confirm bar lengths, laps and chairs with the drawings, and get the base material price per ton or per yard from the quarry.
Common Checks
- Coverage per cubic yard: 81 sq ft at 4 inches, 64.8 sq ft at 5 inches, 54 sq ft at 6 inches. Divide the slab area by the right figure as a quick check.
- Reinforcement only works where it sits. Hold rebar or mesh up in the slab on chairs or bolsters; steel lying on the base does little. Count the chairs in the takeoff.
- Rebar length here is the grid before laps. Bars longer than your stock length need lap splices; the rebar calculator adds them and counts stock bars.
- Under conditioned interior slabs, the International Residential Code (R506.2.3) calls for a 6-mil polyethylene vapor retarder with joints lapped at least 6 inches. Allow extra area for laps and turn-ups.
Concrete Slab Calculator FAQs
How do I calculate cubic yards of concrete for a slab?
Multiply length in feet by width in feet by thickness in inches, divide by 12, then by 27. A 20 × 20 ft slab at 4 inches is 20 × 20 × 0.333 ÷ 27 = 4.94 cubic yards. The shortcut square feet × inches ÷ 324 gives the same answer.
How thick should a concrete slab be?
The International Residential Code (R506.1) sets 3.5 inches as the minimum for slab-on-ground floors. In practice 4 inches is usual for patios, walks and shed pads, and 5 to 6 inches for driveways and garage floors. Slabs carrying heavy vehicles or equipment, and structural slabs, should follow the drawings or an engineer.
How many 80 lb bags of concrete do I need for a slab?
Divide the slab volume in cubic feet by 0.60, the yield Quikrete lists for an 80 lb bag of Concrete Mix. A 12 × 12 ft slab at 4 inches is 48 cubic feet, so 80 bags before waste and 88 with 10 percent added. That much mixing by hand is a long day; above about a yard many people order ready-mix.
How much rebar do I need for a slab?
For a grid, count the bars each way as the span divided by the spacing, rounded up, plus one. A 20 × 20 ft slab at 12 inches on center has 21 bars each way, 840 linear feet in all, which is about 561 lb of #4 bar at 0.668 lb per foot. Add laps and waste for the order; the rebar calculator does that.
Should I use rebar or wire mesh in a slab?
Both control cracking when they are held up in the slab. Welded wire mesh is common in thinner residential flatwork such as patios and walks; rebar grids are common in driveways, garage floors and slabs that carry heavier loads. Follow the drawings or local practice where they apply.
How much gravel do I need under a concrete slab?
Multiply the slab area by the base depth. A 20 × 20 ft slab on a 4-inch base needs 400 × 0.333 ÷ 27 = 4.94 cubic yards of stone before compaction. Use the gravel calculator to convert that to tons with your supplier’s density and compaction allowance.
How much extra concrete should I order for a slab?
Five to ten percent over the measured volume is the usual range. Uneven subgrade, form deflection and spillage all use concrete, and coming up short means a second truck and a cold joint. Rough subgrade or unmeasured thickened edges push you to the top of that range.
Do I need a vapor barrier under a concrete slab?
Under slabs in conditioned living space, yes: the International Residential Code (R506.2.3) requires a 6-mil polyethylene or approved vapor retarder with joints lapped at least 6 inches, with listed exceptions such as garages and unheated accessory buildings. Exterior patios and driveways are normally poured on the compacted base without one.
Estimating Software by Trade
Related Tools & Resources
Turn Calculator Work Into Bids
Estimating Software
Related Calculators
Software Comparisons
From the Blog
Try it on your own plans
Automate your slab takeoffs and quotes.
Spend less time measuring slab plans and rebuilding the same estimate. Get the next quote moving. BuildVision extracts slab areas and measurements from your plans and carries them through your rates and assemblies into a branded quote. Your team checks the quantities and pricing before sending. Try it free on your own plans.
First takeoff free · No card · $299/seat/month after