Construction Calculators

Jump to a tool or explore below.

Free Concrete Calculator

Concrete Calculator

Work out how much concrete you need for a slab, footing, column, wall, stairs or curb. Get cubic yards, cubic feet and cubic meters, bags by size, ready-mix trucks and cost.

Six pour shapes
40–80 lb and 20–25 kg bags
Ready-mix trucks and cost

Concrete Volume, Bag & Cost Calculator

Pick the shape, enter its dimensions, and press Calculate. Imperial uses feet and inches; metric uses meters and centimeters.

Calculator inputs

Covers spillage, form bulge and uneven subgrade. 5–10% is common.

Leave blank to use the yield for the selected bag; enter the yield printed on your product to override.

Enter your local plant's quote.

Planning estimate only. Confirm field measurements, product coverage, local requirements, waste, pricing, and supplier quantities before ordering or bidding.

Concrete Formula and Worked Example

Cubic yards = length (ft) × width (ft) × thickness (in) ÷ 12 ÷ 27
Bags = cubic feet × (1 + waste %) ÷ bag yield (ft³ per bag)

Dividing thickness in inches by 12 turns it into feet, and dividing cubic feet by 27 turns them into cubic yards, because a cubic yard is a 3 × 3 × 3 ft cube. One cubic yard is 0.7646 cubic meters.

Example: a 10 × 10 ft slab, 4 inches thick

  1. Thickness in feet: 4 ÷ 12 = 0.333 ft
  2. Volume: 10 × 10 × 0.333 = 33.3 cubic feet
  3. Cubic yards: 33.3 ÷ 27 = 1.23 yd³ (0.94 m³)
  4. 80 lb bags at 0.60 ft³ each: 33.3 ÷ 0.60 = 55.6, rounded up to 56 bags
  5. With a 10% waste allowance: 36.7 ft³ ÷ 0.60 = 62 bags, or 1.36 yd³ of ready-mix

The same slab takes 75 bags of 60 lb mix before waste. At 1.36 yd³ it fits easily on one 10-yard truck, but a plant will usually add a short-load charge for that little concrete.

Automate your concrete takeoffs and quotes.

Get more concrete quotes out with less time spent measuring drawings and retyping quantities. BuildVision extracts concrete measurements and quantities from your plans and carries them through your rates and assemblies into a branded quote. Your team checks the quantities and pricing before sending. Try it free on your own plans.

How Many Bags of Concrete per Cubic Yard

Bag counts come from the yield printed on the bag. The pound sizes below use the yields in the Quikrete Concrete Mix (No. 1101) data sheet. Metric 20 kg multi-purpose mixes, such as Blue Circle Multi-Purpose Concrete and Easy Mix Concrete, state about 0.01 m³ per bag on their data sheets; the 25 kg row is scaled from that figure. Other brands and high-strength mixes can differ, so check your bag.

Bag sizeYield per bagBags per yd³Bags per m³Yield source
40 lb (18.1 kg)0.30 ft³90118Quikrete data sheet
50 lb (22.6 kg)0.375 ft³7295Quikrete data sheet
60 lb (27.2 kg)0.45 ft³6079Quikrete data sheet
80 lb (36.2 kg)0.60 ft³4559Quikrete data sheet
20 kg (44 lb)0.010 m³7710020 kg mix data sheets
25 kg (55 lb)0.0125 m³6280Scaled from 20 kg

Counts are rounded up to whole bags and include no waste. Add your waste allowance before you buy.

Common Slab Sizes: Yards and Bags

Quick answers for the slabs people pour most. Volumes are exact geometry before waste; bag counts use 0.60 ft³ per 80 lb bag and 0.45 ft³ per 60 lb bag, rounded up.

SlabThicknessCubic yardsCubic feet80 lb bags60 lb bags
4 × 4 ft4 in0.205.3912
8 × 8 ft4 in0.7921.33648
10 × 10 ft4 in1.2333.35675
10 × 12 ft4 in1.4840.06789
12 × 12 ft4 in1.7848.080107
16 × 16 ft4 in3.1685.3143190
20 × 20 ft4 in4.94133.3223297
24 × 24 ft4 in7.11192.0320427
10 × 20 ft5 in3.0983.3139186
20 × 24 ft6 in8.89240.0400534

A handy check: at 4 inches thick, one cubic yard covers 81 square feet. At 5 inches it covers 64.8 square feet, and at 6 inches, 54 square feet.

Volume Formulas by Shape

The calculator uses these formulas. Each gives cubic feet; divide by 27 for cubic yards.

Slab, patio or driveway

L (ft) × W (ft) × T (in) ÷ 12

Flat pours of uniform thickness. Break L-shapes into rectangles.

Continuous footing

L (ft) × W (in) × D (in) ÷ 144

Strip footings under walls; use the total run around the building.

Round column or sonotube

π × (D (in) ÷ 24)² × H (ft)

Piers, post holes and tube forms. D is the inside diameter.

Wall

L (ft) × H (ft) × T (in) ÷ 12

Poured foundation and retaining walls of uniform thickness.

Stairs

W × R × T × n(n+1) ÷ 2 + W × landing × n × R

Solid steps on grade. R and T are riser and tread in feet; n is the number of steps.

Curb and gutter

L (ft) × (curb H × curb W + gutter W × flag T) ÷ 144

Section dimensions in inches; the result is cubic feet.

How Much Does a Yard of Concrete Cost?

Fixr's concrete delivery cost guide (updated January 31, 2025) puts ready-mix at about $125 to $133 per cubic yard before delivery. It lists full-load delivery at about $55 to $65 and short-load charges of about $15 to $17 per yard, and notes that a standard truck carries 10 cubic yards. We checked that page on November 5, 2026.

Your price depends on the plant, the mix strength, additives, distance and season, so the calculator takes your own price per yard (or per cubic meter in metric) and per bag. Pump trucks, finishing labor, forms, base stone and reinforcement are separate lines in a real estimate.

Bags or Ready-Mix?

Bagged concrete

Suits post holes, small pads, steps and repairs. One cubic yard is 45 bags of 80 lb mix, about 3,600 lb to lift, mix and place, so bags get hard work quickly past a yard. Mix in batches small enough to place and finish before they set.

Ready-mix truck

Suits slabs, driveways, footings and walls. You get one consistent batch with a delivery ticket. Order in the increments your plant batches, have the forms, base and crew ready, and confirm access for the truck or a pump.

How the Concrete Calculator Works

A concrete order comes down to one number: cubic yards. Ready-mix plants sell by the yard, bagged mix is labeled by the cubic feet each bag yields, and a metric job is priced in cubic meters. This calculator turns the dimensions of the pour into all three, then converts the order volume into bags of the size you buy and into 10-yard truckloads.

Pick the shape that matches the pour. Slabs, patios and driveways are length × width × thickness. Continuous footings use the total run with the width and depth in inches. Round columns and sonotubes use the inside diameter and height. Walls are length × height × thickness. Stairs add one riser of height for each step, plus an optional top landing. Curb and gutter adds the curb section to the gutter flag. Enter several identical pours with the quantity field, such as twelve piers of the same size.

Bag counts use manufacturer yields: 0.30, 0.375, 0.45 and 0.60 cubic feet for 40, 50, 60 and 80 lb bags of Quikrete Concrete Mix, and about 0.01 m³ for a 20 kg bag of multi-purpose mix. If your bag prints a different yield, type it in and the count follows. The waste allowance is added once, to the order volume, before bags, trucks and cost are worked out.

Concrete volume formulas

  • Slab: cubic yards = length (ft) × width (ft) × thickness (in) ÷ 12 ÷ 27
  • Footing: cubic yards = length (ft) × width (in) × depth (in) ÷ 144 ÷ 27
  • Round column: cubic feet = π × (diameter (in) ÷ 24)² × height (ft)
  • Stairs: cubic feet = width × riser × tread × n(n + 1) ÷ 2, plus width × landing × n × riser
  • Order volume = volume × quantity × (1 + waste % ÷ 100)
  • Bags = order volume (ft³) ÷ bag yield (ft³), rounded up; 1 yd³ = 27 ft³ = 0.7646 m³

Estimating Steps and Checks

1

Break the pour into simple shapes

Split the job into slabs, footings, columns, walls, stairs and curbs. An L-shaped patio is two rectangles; a thickened slab edge is a footing added to the slab. Work out each piece and add them.

2

Measure length and width at the forms

Measure the inside of the forms in feet, or in meters for metric. Forms that are set and braced give a truer number than the plan, which may have changed on site.

3

Measure the thickness or depth in several places

Check the depth in inches at the corners and the middle. Subgrade is rarely flat, and a slab that averages 4.5 inches instead of 4 takes 12.5 percent more concrete. Use the average.

4

Set the waste allowance and quantity

Enter how many identical pours you have, then a waste allowance for spillage, form bulge and uneven ground. Five to ten percent is a common range; use more for rough subgrade or many small pours.

5

Choose bags or ready-mix and price it

Pick the bag size you can buy, or leave it at 80 lb, and enter your price per bag or per yard. Read the bag count, truckloads and cost, then confirm the yield and price with your supplier before ordering.

Common Checks

  • Thickness is the usual mistake. A 4-inch slab is 0.333 ft, not 4 ft. The calculator takes thickness in inches (or centimeters) for that reason.
  • Sanity check: at 4 inches thick, one cubic yard covers 81 square feet; at 6 inches it covers 54. Divide the slab area by that figure and compare it with the result.
  • Bag yields differ by product. High-strength and fast-setting mixes can yield differently from general-purpose mix of the same weight, so read the bag and enter its yield if it differs.
  • Volume is only the concrete. Base stone, forms, rebar or mesh, vapor barrier, pump time, finishing and curing are separate items in an estimate.

Concrete Calculator FAQs

How many bags of concrete do I need for a 10x10 slab?

A 10 × 10 ft slab at 4 inches thick is 33.3 cubic feet, or 1.23 cubic yards. That is 56 bags of 80 lb mix (0.60 ft³ each) or 75 bags of 60 lb mix (0.45 ft³ each) before waste. With a 10 percent waste allowance it is 62 bags of 80 lb mix or 82 bags of 60 lb mix.

How many 80 lb bags of concrete are in a yard?

Forty-five. A cubic yard is 27 cubic feet, and Quikrete lists an 80 lb bag of Concrete Mix at about 0.60 cubic feet, so 27 ÷ 0.60 = 45. A yard takes 60 bags of 60 lb mix, 72 bags of 50 lb mix or 90 bags of 40 lb mix.

How much is a yard of concrete?

Fixr's concrete delivery cost guide, updated January 31, 2025, puts ready-mix at about $125 to $133 per cubic yard before delivery, with full-load delivery around $55 to $65 and short-load charges of about $15 to $17 per yard. We checked it on November 5, 2026. Local plants vary, so enter your own quote in the calculator.

How thick should a concrete slab be?

The International Residential Code (section R506.1) sets 3.5 inches as the minimum for concrete slab-on-ground floors, and 4 inches is the usual thickness for patios, walks and shed pads. Driveways and garage floors are commonly 5 to 6 inches. Slabs for heavy loads, and anything structural, should follow the drawings or an engineer.

What is the difference between concrete and cement?

Cement is one ingredient of concrete. Portland cement is a fine powder that reacts with water and binds the mix together. Concrete is cement, water, sand and gravel or crushed stone. Bagged concrete mix already contains the sand and stone; a bag of cement alone does not.

How many yards of concrete does a truck hold?

A standard ready-mix truck carries up to 10 cubic yards, which is the figure the calculator uses for truckloads. Many plants charge a short-load fee when you order less than a full load, so ask about the minimum before you schedule the pour.

How do I calculate concrete for a round column or sonotube?

Use π × radius² × height. For a 12-inch tube 4 feet tall, the radius is 0.5 ft, so 3.1416 × 0.25 × 4 = 3.14 cubic feet, or 0.12 cubic yards. That is 6 bags of 80 lb mix before waste. Choose "Round column or sonotube" and enter the diameter in inches and height in feet.

How much concrete do I need for a footing?

Multiply the total length of the footing in feet by its width and depth in inches, divide by 144 for cubic feet, then by 27 for cubic yards. A 100-foot run of footing 20 inches wide and 10 inches deep is 138.9 cubic feet, or 5.14 cubic yards before waste.

How much extra concrete should I order?

Most estimators add 5 to 10 percent to the measured volume. Uneven subgrade, forms that bow, spillage and concrete left in the pump or chute all use some. Running short partway through a pour costs far more than a little left over, so lean toward the higher end on rough ground.

How do I calculate concrete for steps?

For solid steps on grade, each step stands one riser taller than the one below it. Volume = width × tread × riser × n(n + 1) ÷ 2, where n is the number of steps, plus width × landing depth × total height for a top landing. Three 7-inch risers with 11-inch treads, 4 feet wide, come to 12.8 cubic feet, or about 0.47 cubic yards.

Try it on your own plans

Automate your concrete takeoffs and quotes.

Get more concrete quotes out with less time spent measuring drawings and retyping quantities. BuildVision extracts concrete measurements and quantities from your plans and carries them through your rates and assemblies into a branded quote. Your team checks the quantities and pricing before sending. Try it free on your own plans.

First takeoff free · No card · $299/seat/month after

Concrete Calculator | Yards, Bags, Trucks & Cost