A cubic yard is a unit of volume equal to a cube 3 feet long, 3 feet wide, and 3 feet deep — 27 cubic feet — and is the standard unit for ordering concrete, gravel, and fill.
A cubic yard is a measure of volume equal to a cube that is 1 yard (3 feet) on each side. Because 3 × 3 × 3 = 27, there are 27 cubic feet in one cubic yard. To convert any volume measured in cubic feet to cubic yards, divide by 27. The unit is abbreviated CY or yd³, and contractors often just say “yards” — as in ordering “ten yards of concrete.”
In US construction, the cubic yard is the standard unit for bulk materials that are placed by volume: ready-mix concrete, excavation and backfill, topsoil, gravel and aggregate base, and mulch. To calculate cubic yards, multiply length × width × depth with all three dimensions in feet, then divide by 27. One cubic yard is approximately 0.7646 cubic meters.
Drawings rarely state cubic yards directly. Instead, the estimator derives volume from plan dimensions and sections: slab area and thickness from the structural plans, footing sizes from foundation details, and cut and fill depths from grading plans. Thickness is the dimension most often shown in inches, so it must be converted to feet before multiplying — a 4-inch slab is 0.333 feet thick, which means one cubic yard of concrete covers 81 square feet at 4 inches.
In the takeoff and bid, concrete and earthwork are carried in CY and priced per cubic yard for material, placement, and equipment. Estimators add a waste factor to concrete for over-excavation, uneven subgrade, and spillage, and they account for swell and compaction on earthwork, because excavated soil occupies more volume loose than it did in the bank and less once compacted. Gravel and aggregate are frequently purchased by the ton, so the estimator converts CY to tons using the supplier’s material weight.
Break each element into simple shapes — slabs, footings, walls, piers — and calculate the volume of each in cubic feet using dimensions in feet, then divide the total by 27. Keep slab-on-grade, footings, and walls on separate lines because they carry different placement costs. The common mistakes are forgetting to convert inches to feet, missing thickened slab edges and turn-down footings shown only in details, and ordering exactly the calculated volume with no allowance for waste. Concrete is typically ordered rounded up, because a short load on pour day is far more expensive than a small surplus.
There are exactly 27 cubic feet in one cubic yard, because a cubic yard is 3 feet × 3 feet × 3 feet. To convert cubic feet to cubic yards, divide by 27; to convert cubic yards to cubic feet, multiply by 27.
Multiply the slab length in feet by the width in feet by the thickness in feet, then divide by 27. For a 20 × 20 foot slab that is 4 inches thick: 20 × 20 × 0.333 = 133.3 cubic feet, divided by 27 = about 4.94 cubic yards, before waste.
It depends on depth. At 4 inches thick, one cubic yard covers 81 square feet; at 6 inches it covers 54 square feet; at 3 inches it covers 108 square feet. Divide 324 by the depth in inches to get square feet of coverage per cubic yard.
No. A cubic yard is a measure of volume, not weight, and different materials weigh different amounts per cubic yard depending on density, gradation, and moisture. When a supplier sells by the ton, use their published weight for that specific material to convert.
Producing accurate cubic yard the manual way takes hours. BuildVision AI reads your drawings and generates structured takeoffs and BOQs in minutes, ready for your own pricing.
Direct from PDF plans, uploaded as one PDF or a ZIP of PDFs.
Itemized bills of quantities ready for pricing or owner submission.
Branded quotes priced with your own rates, shared as a link.
First takeoff free · No card · $299/seat/month after